Project Plan

Introduction​

This project plan is based on a project start date of July 6, 2026. The dates shown are estimated checkpoints and deliveries and are subject to change as planning, implementation, validation, and review progress.

The status values used in this plan are:

StatusDescription
PlannedWork is scheduled but has not started.
In progressWork on the deliverable is underway.
DeliveredThe deliverable has been made available for review.
DoneThe deliverable has completed review and no further work is currently required.

Milestone Deliveries​

MilestoneMilestone TitleEstimated Delivery DateStatus
M1OpenSBI enhancementsOctober 30, 2026In progress
M2Compiler, documentation and CI supportAugust 12, 2026Delivered
M3ASLR and stack-canary validationSeptember 25, 2026Delivered
M4Hardware cryptographic accelerationAugust 27, 2026Delivered
M5RISC-V landing-pad planningSeptember 25, 2026Delivered
M6RISC-V landing padsNovember 16, 2026Planned
M7OP-TEE TA context-switch register managementJuly 22, 2026Delivered
M8Data permissions in OP-TEE coreNovember 16, 2026In progress

Delivery Timeline​

The following is the current delivery plan and is subject to change.

DateMilestoneDescriptionStatusNotes
July 17, 2026M2Initial compiler and documentation work checkpointDeliveredDocumentation and compiler changes merged. The remaining QEMU RISC-V64 CI work is awaiting the merge of the prerequisite MPXY patches.
July 22, 2026M7Trusted-application context-switch register management deliveryDeliveredFP context switch changes merged. Vector patchsets in review cycle.
August 12, 2026M2CI support deliveryDeliveredCI changes awaiting merge of prerequisite MPXY changes.
August 27, 2026M4Hardware cryptography deliveryDeliveredMaintainer review pending upstream until M7 review concludes.
September 25, 2026M3ASLR and stack-canary validation deliveryDeliveredPatches remain under review. Clang build change accepted.
September 25, 2026M5Landing-pad planning documentationDeliveredPlan is under discussion in RISE Platform WG and upstream OP-TEE community.
October 30, 2026M1OpenSBI enhancements deliveryIn progressStarted while waiting for M5 Landing Pad plan feedback. Working on RPMI SYSTEM_IRQ service group implementation in OpenSBI.
November 16, 2026M8Data-permissions deliveryIn progressWork is in early stages of design.
November 16, 2026M6Landing-pad implementationPlannedAwaiting completion of plan feedback.